Project management software tools normally do not promote the use of Facebook as a forum to promote project activities.

A) True
B) False

Correct Answer

verifed

verified

A(n) _____ is a tool used to document, monitor, and track problems that need resolution.


A) requirements traceability matrix
B) Gantt chart  
C) power/interest grid
D) issue log

E) None of the above
F) A) and D)

Correct Answer

verifed

verified

The stakeholder management plan should not be accessible to all stakeholders.

A) True
B) False

Correct Answer

verifed

verified

A(n) _____ is a tool used to group stakeholders based on their level of authority and their level of concern for project outcomes.

Correct Answer

verifed

verified

power/interest grid

Project stakeholder management has only recently been identified as an entire knowledge area by the Project Management Institute.

A) True
B) False

Correct Answer

verifed

verified

Government officials and concerned citizens would be classified as _____ project stakeholders.

Correct Answer

verifed

verified

Though stakeholders cannot be controlled, their level of engagement can be controlled.

A) True
B) False

Correct Answer

verifed

verified

Internal stakeholders include top management, other functional managers, and other project managers.

A) True
B) False

Correct Answer

verifed

verified

The project team must take corrective action if stakeholders with high interest and high power are categorized as _____.


A) resistant
B) neutral  
C) supportive
D) leading

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

A(n) _____ is a tool that helps clarify expectations and lists project measures of success as well as priorities, expectations, and guidelines related to each measure.

Correct Answer

verifed

verified

expectatio...

View Answer

Stakeholders might change during a project due to employee turnover, partnerships, and other events.

A) True
B) False

Correct Answer

verifed

verified

A(n) _____ is a tool that is used to document, monitor, and track problems that need resolution.

Correct Answer

verifed

verified

Doctors who have been co-opted to actively participate in a project related to using information technology for chronic health problems would be examples of _____ stakeholders.


A) supportive
B) leading  
C) resistant
D) neutral

E) B) and C)
F) A) and B)

Correct Answer

verifed

verified

B

Scope, time and cost goals in order of importance can be ranked on a(n) _____.


A) requirements traceability matrix
B) expectations management matrix  
C) responsibility assignment matrix
D) probability matrix

E) A) and C)
F) A) and B)

Correct Answer

verifed

verified

_____ is the new knowledge area identified by the Project Management Institute.


A) Project stakeholder management
B) Project communication management  
C) Project risk management
D) Project procurement management

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

Issue logs can be used to address issues related to other knowledge areas like project scope management or project quality management.

A) True
B) False

Correct Answer

verifed

verified

_____ involves monitoring stakeholder relationships and adjusting plans and strategies for engaging stakeholders as needed.


A) Planning stakeholder management
B) Identifying stakeholders  
C) Managing stakeholder engagement
D) Controlling stakeholder engagement

E) B) and C)
F) All of the above

Correct Answer

verifed

verified

Project stakeholder management has resonances with project cost management and project time management.

A) True
B) False

Correct Answer

verifed

verified

_____ are individuals, groups, or organizations who may affect, be affected by, or perceive themselves to be affected by a decision, activity, or outcome of a project.

Correct Answer

verifed

verified

Project stakeholders

The main output of the _____ process is the stakeholder register.


A) Planning stakeholder management
B) Identifying stakeholders  
C) Managing stakeholder engagement
D) Controlling stakeholder engagement

E) A) and D)
F) B) and C)

Correct Answer

verifed

verified